New Jersey hits data center powering Microsoft Copilot with $1m fine after drone expose 62 secretly-installed gas generators
- New Jersey issues $1.07m fine for failure to obtain permits to run gas generators
- DataOne campus running Microsoft’s AI was using 62 of them illegally
- DataOne “disagree[s]” but has 45 days to obtain the relevant permits
A Microsoft partner has been hit with a $1.07 million fine by the US state of New Jersey after allegedly installing no fewer than 62 natural gas generators on-site without obtaining the correct environmental permits.
The state found out about the generators after a local farmer photographing a neighboring golf course noticed equipment appearing on the campus, which led to an investigation and the deployment of a thermal drone, which at the time, observed 45 of the 62 generators in operation.
The fine was based on New Jersey’s Air Pollution Control Act, which requires both reconstruction permits to install the generators and operating certificates to run them. Neither had been obtained across all 62 units, the department said in an announcement.
Latest Videos FromTechRadar
Microsoft has been running 62 generators illegally at just one campus
DEP Commissioner Ed Potosnak described the fine as “by far the largest ever taken against a data center in New Jersey and possibly one of the largest such actions in the nation.”
With each generator rated at 1,982 kilowatts, they collectively have a 123-megwatt capacity. For reference, the state asserted that any individual generators with a 37kW or higher capacity should be approved.
The generators effectively provide the data center with a considerable amount of off-grid electricity supply, but while this may be good news to alleviate strains on local infrastructure and household energy prices, CO2, NO2 and CO emissions are particularly concerning.
“While we disagree with the temporary generator determination, we will apply for the air permits for the temporary generators and are in communication with the Department of Environmental Protection regarding its findings and the fuel cell transition timeline,” DataOne, the company behind the data center, said in a statement.
Sign up to the TechRadar Pro newsletter to get all the top news, opinion, features and guidance your business needs to succeed!
DataOne has been given 45 days to obtain the relevant permits, but in the interim, it can continue using the gas generators.
“The Sherrill administration demands accountability and corporate responsibility in the construction and operation of data centers,” Potosnak added.

Follow TechRadar on Google News and add us as a preferred source to get our expert news, reviews, and opinion in your feeds.
New Jersey issues $1.07m fine for failure to obtain permits to run gas generators DataOne campus running Microsoft’s AI was using 62 of them illegally DataOne “disagree[s]” but has 45 days to obtain the relevant permits A Microsoft partner has been hit with a $1.07 million fine by the US…
Recent Posts
- Tesla’s Optimus robot is going through growing pains
- Keychron Thunderbolt 5 Dock review: Unusually sensible
- New Jersey hits data center powering Microsoft Copilot with $1m fine after drone expose 62 secretly-installed gas generators
- Sony and UMG are suing Suno again
- Looking for your next Fujifilm lens? These top 12 primes and zooms cover any situation
Archives
- September 2026
- August 2026
- July 2026
- June 2026
- May 2026
- April 2026
- March 2026
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- March 2025
- February 2025
- January 2025
- December 2024
- November 2024
- October 2024
- September 2024
- August 2024
- July 2024
- June 2024
- May 2024
- April 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- October 2023
- September 2023